PROJECT OVERVIEW
Full basement finishing package including epoxy floor coating system (400 sq ft), full kitchen cabinet installation, interior painting (walls, ceiling, trim), and bathroom vanity installation. All work performed by First Due Epoxy Systems with licensed subcontractors as needed. Client to supply cabinets and vanity unit unless otherwise noted.
01 — EPOXY FLOOR SYSTEM
Description Qty Unit Rate Total
Surface Prep & Concrete Grinding
Diamond grind full floor, edge work, crack/joint inspection
400sq ft$1.50$600
PE-85 Polyurea Crack & Joint Filler
Fill all cracks, control joints, and surface defects
1kit$75$75
CP-8355 Base Coat (Flake Broadcast System)
100% solids base coat, full flake broadcast to rejection
400sq ft$2.25$900
Decorative Flake
Client's choice of color blend, full broadcast
1bulk bag$150$150
RS-EP-100 Clear Topcoat (2 coats)
High-build clear 100% solids topcoat with aluminum oxide antiskid
400sq ft$2.75$1,100
Labor — Application & Finishing
2-man crew, ~14 hrs on-site
1job$700$575
Epoxy Floor Subtotal $3,200
02 — KITCHEN CABINET INSTALLATION
Description Qty Unit Rate Total
Cabinet Installation — Labor Only
Client supplies cabinets. Full upper & lower install, leveling, securing, and alignment
20lin ft$110$2,200
Hardware & Fasteners
Screws, shims, anchors, misc supplies
1lot$75$75
Trim & Touch-Up Caulking
All cabinet seams, wall gaps, and finish lines
1job$125$125
Cabinet Installation Subtotal $2,400
03 — INTERIOR PAINTING
Description Qty Unit Rate Total
Wall Prep — Patch, Sand & Prime
Skim patch all holes/imperfections, sand, 1 coat primer
1,600sq ft$0.625$1,000
Interior Wall Paint (2 coats)
Client's choice of color, premium latex, cut & roll
1,600sq ft$1.75$2,800
Ceiling Paint (1 coat)
Flat white ceiling paint, full coverage
400sq ft$1.00$400
Trim & Baseboards (2 coats semi-gloss)
All door casings, window trim, and base molding
1job$350$350
Paint Materials
Primer, paint (approx. 6 gallons), tape, drop cloths, rollers
1lot$250$250
Painting Subtotal $4,800
04 — BATHROOM VANITY INSTALLATION
Description Qty Unit Rate Total
Vanity Installation — Labor Only
Client supplies vanity unit. Remove existing, set and level new vanity, reconnect plumbing supply lines
1job$400$400
Plumbing Supply Line Connection
Hot/cold supply, P-trap, drain connection. Does not include rough plumbing modifications.
1job$125$125
Caulk & Finish
Seal all perimeter joints, touch-up around vanity
1job$75$75
Vanity Subtotal $600
Epoxy Floor System$3,200
Cabinet Installation$2,400
Interior Painting$4,800
Vanity Installation$600
Subtotal$11,000
Tax (included)
TOTAL ESTIMATE$11,000
Payment Schedule
50% Deposit / 50% on Completion
Deposit due before work begins
Estimated Timeline
5–7 Business Days
Weather & material delivery dependent
Estimate Valid
30 Days
From date of issue
Warranty
1 Year Labor
Epoxy system manufacturer warranty separate
Important Notes
  • Client responsible for supplying all cabinets and vanity unit prior to installation date.
  • Epoxy system requires 24hr cure before light foot traffic, 72hr before full use. Furniture must be cleared from floor area before work begins.
  • Paint colors to be selected by client prior to project start. Any color changes after work begins may incur additional charges.
  • This estimate does not include rough plumbing, electrical, drywall repair, or flooring outside the designated epoxy area.
  • Any unforeseen conditions discovered during work (significant concrete damage, mold, structural issues) will be documented and quoted separately before proceeding.
  • Final invoice may vary ±10% from estimate based on actual site conditions.
Contractor
Chris Correa
First Due Epoxy Systems
Signature / Date
Client Acceptance
[Client Name]
By signing, client accepts this estimate and authorizes work to begin upon receipt of deposit.
Signature / Date